(A) General. All building service equipment for which a permit is
required by this chapter or the technical codes shall be inspected by the
building official. No portion of any building service equipment shall be
concealed until inspected and approved. When the installation of any building
service equipment is complete, a final inspection shall be performed. Building
service equipment regulated by the technical codes shall not be connected to the
water, fuel or power supply or sewer system until authorized by the building
official.
(B) Replacement of Building Service Equipment. Building service
equipment installed to replace existing building service equipment which is
serving an occupied portion of the building may be operated if a request for
inspection of that replacement equipment has been filed with the building
official not more than forty-eight hours after such replacement work was
completed and before any portion of the building service equipment is
concealed.
(C) Performance Verification. Prior to final inspection of the
building, the appropriate permittee is responsible to test all components of the
fire and life-safety systems and verify their proper operation.
Upon
completion of all component testing, the general contractor shall perform an
overall life-safety system test. The system test program shall be submitted to
the building official prior to system testing. The system test shall be
witnessed by the building official. (Ord. 3618 § 2 (part), 2008)