22.02.300 Phased design and construction.

(A) General. The building official may authorize projects to be constructed using a phased design and construction approach. However, such authorization must be obtained prior to submission of construction documents. Final authorization of projects to be constructed using a phased design and construction approach shall be determined by the building official.
(B) Application. The applicant shall furnish all information as may be required by the building official, including the following:
(1) Description of the project including preliminary drawings, if any;
(2) Description of the land by parcel(s) on which the project is to be built;
(3) And the applicant’s actions to date to obtain proper zoning;
(4) Design and construction schedule outlining time-phases of the project;
(5) A description of each time-phase showing what construction is to be completed in that phase;
(6) The name of the person who will be responsible for coordinating the phasing, plans submittals, design data, resubmittals, correspondence and meetings with the applicant’s organization and the department;
(7) The name of the principal design professional for the project; and
(8) A statement indicating the final phase for which the coordinating person will be responsible under this application. All work subsequent to this phase shall be governed by other provisions of this chapter and the technical codes.
(C) Procedure. All submittals to the building official shall be accompanied by a letter of transmittal listing the documents, describing their contents and stating the purpose of the transmittal. All documents resubmitted which have been revised or changed in whole or part shall contain a revision date and an indication of the type and location of revisions or changes made. Significant revisions or changes to the documents shall be made in an identical manner of delineation as the original submitted documents. (Ord. 3618 § 2 (part), 2008)