22.02.295 Building permit issuance.
The permit application and construction documents filed by an
applicant for construction or installation permits shall be reviewed by the
building official. The construction documents may be reviewed by other
departments of Clark County to verify compliance with any applicable laws. The
building official shall require the application for permit to include
verification of applicable services, including, but not limited to, water and
sewer, prior to the issue of construction permits. As a prerequisite to
obtaining a building permit or combination permit all fees for the permit, the
residential construction tax (if any), the multiple species habitat conservation
plan mitigation fee (if any), and the transportation tax (if any) must be paid
prior to issuance. If the building official finds that the work described in an
application for a permit and the construction documents filed with it conform to
the requirements of this chapter, the technical codes and other pertinent laws
and ordinances, the building official shall endorse in writing or stamp the
plans and specifications “APPROVED.”
Approved construction
documents shall not be changed, modified or altered without authorization from
the building official, and all work required by this chapter shall be done in
accordance with the approved construction documents. Upon identification and
verification of appropriate licensing of a contractor and the payment of fees
pursuant to this chapter, a permit shall be issued to the contractor for the
work described.
The building official may issue a permit for the
construction of part of a building, structure or building service equipment
before the construction documents for the entire building, structure or building
service equipment have been submitted or approved, provided adequate information
and detailed statements have been submitted with the application to show
compliance with the requirements of this chapter and the technical codes.
Issuance of the permit does not assure that a permit for the entire building,
structure, or building service equipment will be granted and the permittee shall
proceed at his own risk. Note: See “phased design and construction.”
(Ord. 3618 § 2 (part), 2008)